2011 Reaffirmation of Accreditation
Schedule of Activities
- Spring and Summer 2008
- Identify gaps in policy, procedures and evidence
- Implement Xitracs compliance tracking system
- Fall 2008
- Remediate gaps
- Draft responses
- Upload evidence
- Develop approach to faculty qualifications
- Spring 2009
- Remediate gaps
- Review responses
- Upload evidence
- Test faculty roster
- Orientation of Leadership Team on June 8
- Fall 2009
- Remediate gaps
- Modify responses
- Upload evidence
- Generate Fall 2009 faculty roster
- Spring 2010
- Finalize responses and evidence
- Generate Spring 2010 faculty roster
- Send draft to editor
- Fall 2010
- Launch compliance certification web site
- Compliance certification on September 10
- Off-site peer review in November
- Address recommendations from off-site review
- Spring 2011
- Submit Quality Enhancement Plan
- Prepare for on-site review
- On-site review conducted
- Address recommendations from on-site review
- Fall 2011
- Reaffirmation decision in December